How to File a Construction Lien in Ontario (Step-by-Step 2026 Guide)
How to File a Construction Lien in Ontario
The Ontario Construction Act (formerly the Construction Lien Act) protects contractors, subcontractors, and suppliers who aren't paid for work or materials. Filing a construction lien is a powerful legal tool — but the deadlines are strict. Miss them, and you lose your rights entirely.
Who Can File a Lien?
Under the Ontario Construction Act, anyone who supplies services or materials to an "improvement" can file a lien:
Critical Deadlines
The 60-Day Rule: You must preserve your lien within 60 days of the last day you supplied services or materials to the project. This is non-negotiable.
The 90-Day Rule: After preserving the lien, you have 90 days to perfect it by starting a court action.
|--------|----------|----------------------|
Step-by-Step Filing Process
Step 1: Calculate Your Deadline
Count 60 days from the last day you performed work or supplied materials. If the project has been certified as "substantially complete," the 60-day clock starts from that certification date.
Step 2: Prepare the Claim for Lien
Your lien document must include:
Step 3: Register the Lien
File the Claim for Lien at the Land Registry Office (now ServiceOntario) where the property is located. The registration fee is approximately $70-$100.
Step 4: Serve the Lien
Serve a copy of the registered lien on the property owner within 30 days of registration.
Step 5: Perfect the Lien
Within 90 days of preservation, you must commence a court action. File a Statement of Claim in the Superior Court of Justice.
The 10% Holdback Rule
Ontario law requires every person who pays for construction work to hold back 10% of the price of the work/materials for 60 days. This holdback creates a trust fund that protects subcontractors and suppliers.
Costs Involved
|------|------|
Common Mistakes
Alternatives to Filing a Lien
Before filing a lien, consider:
Use our free Lien Generator tool to create Ontario-compliant lien documents instantly.
- General contractors
- Subcontractors (all tiers)
- Material suppliers
- Equipment rental companies
- Architects and engineers (for services related to construction)
| Action | Deadline | What Happens If Missed |
|---|---|---|
| Preserve lien (register on title) | 60 days from last work | Lien rights expire permanently |
| Perfect lien (start lawsuit) | 90 days from preservation | Lien expires and is discharged |
| Holdback release | 60 days after substantial completion | Owner can release holdback |
- Your name and address
- The owner's name and address
- A description of the property (legal description)
- The amount claimed
- A description of the services/materials provided
- The date of last supply
- The holdback applies to every level of the payment chain
- If an owner pays the full amount without holding back 10%, they may be liable to lien claimants
- The holdback can be released 60 days after the contract is substantially completed (if no liens are preserved)
| Item | Cost |
|---|---|
| Lien registration | $70–$100 |
| Legal fees (preservation) | $500–$1,500 |
| Legal fees (perfection/lawsuit) | $2,000–$10,000+ |
| Court filing fees | $250–$400 |
- Miscalculating the 60-day deadline — Count carefully from the LAST day of work
- Wrong property description — Must match the legal description exactly
- Liening the wrong property — Condos and subdivisions have specific rules
- Not perfecting within 90 days — The lien expires automatically
- Not serving the owner — Service is required within 30 days of registration
- Sending a demand letter (use our free template)
- Negotiating a payment plan
- Filing a complaint with the Ontario College of Trades
- Using our Should I Sue? Assessment tool